● 某公司的销售收入状态如下表所示,该公司达到盈亏平衡点时的销售收入是(60) (百万元人民币)。
项 |
金额(单位百万元人民币) |
销售收入 |
800 |
材料成本 |
300 |
分包费用 |
100 |
固定生产成本 |
130 |
毛利 |
270 |
固定销售成本 |
150 |
利润 |
120 |
(60)A.560 B.608 C.615 D.680
● 某公司需要根据下一年度宏观经济的增长趋势预测决定投资策略。宏观经济增长趋势有不景气、不变和景气 3 种,投资策略有积极、稳健和保守 3 种,各种状态的收益如下表所示。基于 maxmin 悲观准则的最佳决策是 (61) 。
预计收益(单位百万元人民币) |
经济趋势预测 | |||
不景气 | 不变 | 景气 | ||
投资策略 |
积极 |
50 |
150 |
500 |
稳健 |
100 |
200 |
300 | |
保守 |
400 |
250 |
200 |
(61)A.积极投资 B.稳健投资 C.保守投资 D.不投资
● 风险的成本估算完成后,可以针对风险表中的每个风险计算其风险曝光度。某软件小组计划项目中采用 50 个可复用的构件,每个构件平均是 100LOC,本地每个 LOC 的成本是 13 元人民币。下面是该小组定义的一个项目风险:
1.风险识别:预定要复用的软件构件中只有 50%将被集成到应用中,剩余功能必须定制开发;
2. 风险概率:60%;
3. 该项目风险的风险曝光度是 (62) 。
(62)A. 32500 B. 65000 C. 1500 D. 19500
● 下图标出了某地区的运输网。
各结点之间的运输能力如下表: (单位:万吨/小时)
① | ② | ③ | ④ | ⑤ | ⑥ | |
① | 6 | 10 | 10 | |||
② | 6 | 4 | 7 | |||
③ | 10 | 1 | 14 | |||
④ | 10 | 4 | 1 | 5 | ||
⑤ | 7 | 14 | 21 | |||
⑥ | 5 | 21 |
从结点①到结点⑥的最大运输能力(流量)可以达到 (63) 万吨/小时。
(63)A. 26 B. 23 C. 22 D. 21
● 业主单位授予监理单位的权力,应明确反映在(64) 中,据此项目监理机构才能开展监理活动。
(64)A.监理合同 B.监理大纲 C.监理规划 D.监理计划
● 下列不能作为监理依据的是(65) 。
(65)A.现行国家、各省、市、自治区的有关法律、法规
B.国际、国家 IT 行业质量标准
C.业主单位和承建单位的合同
D.承建单位的指令
● (66) from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
(66)A.Process B.Milestone C.Work D.Deliverables
● Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are (67) .
(67)A.confused B.same C.overlap D.dissever
● In the project management context, (68) includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.
(68)A.integration B.scope C.process D.charter
● Project (69) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
(69)A.Integration B.Scope C.Configuration D.Requirement
● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
(70)A.time estimating B.cost estimating
C.project planning D.schedule development
● In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including(71) 。
(71)A.budget B.plan C.risk D.contract
● Project Quality Management must address the management of the project and the (72) of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.
(72)A.performance B.process C.product D.object
● (73) is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.
(73)A.Problem B.Grade C.Risk D.Defect
● Project (74) Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
(74)A.Integration B.Time C.Planning D.Communication
● The (75) process analyzes the effect of risk events and assigns a numerical rating to those risks.
(75)A.Risk Identification B.Quantitative Risk Analysis
C.Qualitative Risk Analysis D.Risk Monitoring and Control